Bar Bending Schedule for Neck Column / Estimation of Steel reinforcement in Neck Column:-
Bar Bending schedule plays a very important role in estimating quantities of steel reinforcement required for the building. Before getting into Bar bending schedule for Neck Column, I refer you to learn the how to Calculate Bar Bending Schedule (basics) and how to adopt Concrete Cover for Steel reinforcement.
Contents
- Neck column:
- QUANTITY OF REINFORCEMENT (STEEL) REQUIRED FOR NECK COLUMN OR Bar Bending Schedule for Neck Column :-
- CALCULATION FOR THE QUANTITY OF NECK COLUMNS (MAIN BARS):-
- CALCULATION FOR THE QUANTITY OF NECK COLUMNS (STIRRUPS):-
- ABSTRACT FOR FINDING OUT THE TOTAL QUANTITY OF STEEL REINFORCEMENT REQUIRED FOR NECK COLUMN FOR THE ABOVE GIVEN PLAN:-
Neck column:
The part of the column which is present in sub structure is called neck column. (Column in substructure)
Well, the reason for this dividing column into two parts is to make ease in understanding the Bar Bending schedule clearly.
QUANTITY OF REINFORCEMENT (STEEL) REQUIRED FOR NECK COLUMN OR Bar Bending Schedule for Neck Column :-
In this post, I am finding out the Estimation of Steel reinforcement in Neck Column/ Bar Bending Schedule for Neck column. For this, I considered a plan as shown below.
Steps to be followed while finding out the total wt. of steel required for constructing Neck columns: –
Neck column reinforcement calculation is divided into two parts Main bars and stirrups.
Part-I:- Main Bars
- Check the Length of Main bars
- Add the overlap length and bend length to the neck column.
- Adopt Dia of Main Bars
- Calculate the total length of main bar.
- Find the total wt of Main bars.
Part-II:- Stirrups
- Deduce the concrete cover from all sides of tie/stirrups and find out the length of stirrup.
- Adopt Dia of Stirrup.
- Calculate the length of stirrup including hook.
- Then Find out the total no. of stirrups.
- Find the total length of stirrups
- Lastly, Calculate the total wt. of stirrups.
Length, Dia and No. of Bars are adopted and designed by the structural engineer by executing the load analysis.
To make it clear I included almost all types of columns. Well C1, C3, C4, C6, C9 (Square Columns) are similar and C2, C8 (T-Column) C5 is Circular Column, C7 is L Type column.
You can also refer different types of columns.
Assume for calculation:-
Dia of Main Bars = 16mm, Dia of Stirrups= 8mm, Spacing between stirrups = 0.1m.
Length of Main bar excluding extra bars is 2.25m , Diameter of Circular column C5 = 0.6
No. of Main Bars = 4 in Square column, No. of Main Bars = 8 in Circular & L Type Column
No. of Main Bars = 10 in T Type Column
Column Details:-
C1, C3,C4, C6, C9 is Square Column (0.4mx 0.4m)
C5 Circular Column (Radius 0.3m)
C2, C8 T-Type Column
C7 L-Type Column
CALCULATION FOR THE QUANTITY OF NECK COLUMNS (MAIN BARS):-
C1, C3,C4, C6, C9 is Square Column (0.4mx 0.4m):-
C5 Circular Column:-
Well, L Type Column (C7) has same No. of Main Bars as circular column C5, total wt of steel required for L type columns are 41.78 Kgs.
C2, C8 T-Type Column:-
CALCULATION FOR THE QUANTITY OF NECK COLUMNS (STIRRUPS):-
C1, C3,C4, C6, C9 is Square Column (0.4mx 0.4m)
First of all deduct the concrete cover from all the sides of column for finding out the length of stirrup.
As per the condition deduct the concrete cover of 0.05 from all sides of stirrups in square column.
C5 Circular Column (Diameter 0.6m):-
First of all deduct the concrete cover from all the sides of column for finding out the length of stirrup.
As per the condition deduct the concrete cover of 0.1 from all sides of stirrups in square column.
C2,C8 T-Type Column :-
C7 L-Type column: –
ABSTRACT FOR FINDING OUT THE TOTAL QUANTITY OF STEEL REINFORCEMENT REQUIRED FOR NECK COLUMN FOR THE ABOVE GIVEN PLAN:-
Bar Bending Schedule for Footings
Bar Bending Schedule for Tie Beams / Strap Beams
Don’t Forget to Share With your friends! Sharing is Caring:)
For Instant updates Join our Whatsapp Broadcast. Save our Whatsapp contact +919700078271 as Civilread and Send us a message “JOIN”
Never Miss an update Click on “Allow US” and make us allow or Click on Red notification bell at bottom right and allow notifications.
Stay tuned! More are updated Soon!!.
Civil Read Wishes you ALL the BEST for your future..
please join me your what’s app group for future updates 9843600933
send us a message to 970078271 as JOIN in whatsapp we try t add u as soon as possible
Country code please
please help me for given a format of bar bending schedule pf footing and column as soon as possible.
Thank you. It was so easy to understand.
Cheers! i made u to understand!
thanku so much we have getting more doubts clarification in this calculation.
thanku so much bro.
Thanks sir👍👍👍👍
Thank you so much. Very informative to civil engineers
thanku so much we have getting more doubts clarification in this calculation.
Please shall you add for concrete sharewall steel
Sure
very very thanks.. your blog is very mush easy to understand,…
very very thanks your blog is very must easy to understand.